Multiple Choice
An organization requires secure configuration baselines for all platforms and technologies that are used. If any system cannot conform to the secure baseline, the organization must process a risk acceptance and receive approval before the system is placed into production. It may have non-conforming systems in its lower environments (development and staging) without risk acceptance, but must receive risk approval before the system is placed in production. Weekly scan reports identify systems that do not conform to any secure baseline. The application team receives a report with the following results:
There are currently no risk acceptances for baseline deviations. This is a mission-critical application, and the organization cannot operate if the application is not running. The application fully functions in the development and staging environments. Which of the following actions should the application team take?
A) Remediate 2633 and 3124 immediately.
B) Process a risk acceptance for 2633 and 3124.
C) Process a risk acceptance for 2633 and remediate 3124.
D) Shut down NYAccountingProd and investigate the reason for the different scan results.
Correct Answer:

Verified
Correct Answer:
Verified
Q995: A security administrator wishes to implement a
Q996: An organization's policy requires users to create
Q997: A systems administrator needs to integrate multiple
Q998: A corporation is concerned that, if a
Q999: A security administrator receives alerts from the
Q1001: Which of the following provides the ability
Q1002: During a lessons learned meeting regarding a
Q1003: The IT department needs to prevent users
Q1004: Which of the following would allow for
Q1005: After discovering a security incident and removing