Multiple Choice
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?
A) During the planning phase, the project manager should have recognized the relationship between the vendor's and project team's tasks and adjusted the schedule for the project team to begin activities two months later.
B) The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
C) During the project team's regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
D) During the project team's regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.
Correct Answer:

Verified
Correct Answer:
Verified
Q275: Which of the following documents should be
Q276: Which of the following describes risk mitigation?<br>A)
Q277: Several team members report that meeting objectives
Q278: At a weekly project team meeting, it
Q279: When a risk event occurs, which of
Q281: A project manager is starting a project
Q282: Which of the following metrics demonstrates to
Q283: A project manager is trying to explain
Q284: A company has dictated project scope changes
Q285: Which of the following defines a group