During a CCB, a SME Evaluated the Impact and Provided

Question 329

Multiple Choice

During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?


A) Incident response
B) Project plan
C) Risk register
D) Business continuity plan

Correct Answer: