Multiple Choice
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
A) Description, cost difference of the replacement, and WBS
B) Description, justification, and cost
C) Cost difference of the replacement, justification, and communications plan
D) Description, quality impact, and cost
Correct Answer:

Verified
Correct Answer:
Verified
Q108: Which of the following is the BEST
Q109: On larger projects, a vendor may occasionally
Q110: Which of the following are characteristics of
Q111: A client has provided a list of
Q112: The project manager is running a project
Q114: A non-stakeholder approaches the project manager and
Q115: A project manager needs to identify the
Q116: A project coordinator logs potential events that
Q117: Which of the following represents the order
Q118: During the planning phase, the project manager