A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account: Delivery Vacation Cost of overtime Work effort Which of the following documents should the project manager use to guarantee the project's success?
A) RACI
B) Schedule
C) Project charter
D) SWOT
E) Burn chart
Correct Answer: