Multiple Choice
A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO) , the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
A) Have the team members deny all change requests from this stakeholder
B) Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
C) Contact the key stakeholder to encourage the submission of written change requests
D) Request additional resources from the project team to complete the change requests from the key stakeholder
Correct Answer:

Verified
Correct Answer:
Verified
Q510: Which of the following includes setting governance
Q511: A project schedule lists a resource as
Q512: Team members have reported that meetings are
Q513: A project team has failed to deliver
Q514: Which of the following inherently affects quality
Q516: On an OBS chart, there is a
Q517: Due to a new government regulation, a
Q518: A team lead informs the project manager
Q519: A project manager is trying to ensure
Q520: A project's key stakeholders have requested significant