During a Project, the Project Manager Discovers There Is Insufficient

Question 265

Multiple Choice

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.   Given the attached chart, which of the following is the critical path if one day is added to each task for quality control? A)  12 days B)  16 days C)  17 days D)  22 days Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?


A) 12 days
B) 16 days
C) 17 days
D) 22 days