In a Scrum Project, When Would a Requirement Get Added

Question 33

Multiple Choice

In a Scrum project, when would a requirement get added to the Product backlog?


A) When it is developed, but cannot yet be released.
B) When the team works on it for a particular release.
C) When the customer requests a new requirement.

Correct Answer: