Multiple Choice
The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?
A) The team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.
B) The team and the Scrum Master. The Product Owner should be consulted.
C) The team only. The Product Owner should be consulted.