Multiple Choice
Why does the Daily Scrum need to be held at the same location and time?
A) The booking of a room needs to be done in advance for the duration of the Sprint.
B) The constant time and place is best for continuity of the Scrum framework.
C) The Project Manager needs to get the status updates at a given time every day.
Correct Answer:

Verified
Correct Answer:
Verified