Multiple Choice
A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points. Which statement is true regarding this scenario?
A) Points are assigned by the Scrum Master, not by the team.
B) Points are assigned for the overall Story, not for parts of the Story.
C) Points are never estimated, but always determined beforehand.
D) The team forgets to ask the Product Owner about the estimate.
Correct Answer:

Verified
Correct Answer:
Verified
Q59: What happens with the User Stories during
Q60: A team is estimating story points. They
Q61: Who knows most about the progress towards
Q62: One of the Scrum Team members has
Q63: What is meant by the velocity of
Q65: Near the end of a Sprint, the
Q66: What is a characteristic of a well-designed
Q67: What is an information radiator?<br>A) A physical
Q68: Product Backlog Items must be non-technical and
Q69: Your team uses a Kanban board to