Multiple Choice
Which of the following is NOT involved in risk control?
A) Executing the risk response strategy
B) Initiating contingency plans
C) Establishing a change control system
D) Establishing contingency funds
E) Watching for new risks
Correct Answer:

Verified
Correct Answer:
Verified