Multiple Choice
A key distinction between a risk response and a contingency plan is
A) A risk response is established only for moderate risks while contingency plans are established for major risks.
B) A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.
C) A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.
D) A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Why might an organization be opposed to
Q15: When considering risk value, the lower the
Q42: Risks that can result in a system
Q44: Including the change control system within the
Q48: The attempt to recognize and manage potential
Q49: Tools such as a risk assessment form
Q50: Which of the following is identified to
Q55: Which of the following is NOT included
Q89: What is Change Control Management and what
Q94: The risk identification process should be limited