An Administrator Has Two Clusters: Site a and Site B

Question 22

Multiple Choice

An administrator has two clusters: Site A and Site B. Async DR is configured between the clusters as follows: Site A is the Primary Site Site B is the Secondary inactive Site, no VMs running Site A is fully in Production Site B used as Backup/Disaster Recovery The customer wants to perform a planned failover between the sites. How should the administrator accomplish this?


A) Click Activate on the Secondary site within the Data Protection Dashboard
B) Click Activate on the Secondary site and run deactive NCLI command on Primary site
C) Choose Migrate on the Secondary site within the Data Protection Dashboard
D) Choose Migrate on the Primary site within the Data Protection Dashboard