Which Statement About the 'Change Enablement' Practice Is CORRECT

Question 151

Multiple Choice

Which statement about the 'change enablement' practice is CORRECT ?


A) Standard changes are those that need to be scheduled, assessed and authorized following a standard process
B) Normal changes are triggered by the creation of a change request which can be created manually or automated
C) Assessment and authorization of normal changes should be expedited to ensure they can be implemented quickly
D) There should be a separate change authority for standard changes which includes senior managers who understand the risks involved

Correct Answer: