What Is the PRIMARY Use of a Change Schedule

Question 82

Multiple Choice

What is the PRIMARY use of a change schedule?


A) To support the 'incident management' practice and improvement planning
B) To manage emergency changes
C) To plan changes and help avoid conflicts
D) To manage standard changes

Correct Answer: