Multiple Choice
Due to the complexity of a project, the project board is concerned that the business analyst (BA) will not be able to ensure all requirements are verified. What tool can the BA present to the project board to mitigate their concern?
A) Data model
B) Use case diagram
C) Business analysis checklist
D) Risk register
Correct Answer:

Verified
Correct Answer: