Question 453

Multiple Choice

During a retrospective, the project team agrees the way they organized the user stories during the first sprint could be improved. The business analyst (BA) plans to make the stories more accessible going forward. Which of the following will the BA update?


A) Organizational performance standards
B) Information management approach
C) Business analysis performance assessment
D) Project lessons learned register