During the Testing Phase, a New Requirement Surfaced and the Stakeholder

Question 316

Multiple Choice

During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the business analyst (BA) . The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:


A) stakeholder engagement plan
B) change control process
C) risk strategy
D) prioritization approach

Correct Answer: