Multiple Choice
You work as a project manager for TYU project. You are planning for risk mitigation. You need to quickly identify high-level risks that will need a more in-depth analysis. Which one of the following approaches would you use?
A) Risk mitigation
B) Estimate activity duration
C) Quantitative analysis
D) Qualitative analysis
Correct Answer:

Verified