Multiple Choice
What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
A) 40 hours
B) 45 hours
C) 50 hours
D) 55 hours
E) 60 hours