Training Cost Is $4,000 and a Project Required an Initial

Question 110

Multiple Choice

Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months (before money costs and taxes) ?


A) 10
B) 20
C) 27
D) 33