Multiple Choice
Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months (before money costs and taxes) ?
A) 10
B) 20
C) 27
D) 33
Correct Answer:

Verified
Correct Answer:
Verified