Multiple Choice
If a Six Sigma project was to reduce changeover times and the team found the project success was decreasing over time since changeover times began to creep back up, which Lean tools should be considered in the Control Phase to reestablish and sustain the project success?
A) Improve the lighting to assure adequate visibility
B) Confirm a Visual Factory exists to assure proper communication of status of machines
C) Implement Kanbans to assure enough inventory for the process step
D) Reword the standardized work instructions to use active verbs and not passive phrases
Correct Answer:

Verified
Correct Answer:
Verified
Q130: Assessing process proportion as opposed to evaluating
Q131: The Hardware Store ordered ten lawn mower
Q132: When the Inputs, X's, for your process
Q133: Special Cause Variation falls into which two
Q134: Upon completion and validation of an improvement
Q136: Following the completion of a LSS project
Q137: A Belt working in a supply chain
Q138: Following process modifications, the Null Hypothesis states
Q139: Which Experimental Design typically is most associated
Q140: A Belt rearranged the location of the