Mary Is Scheduled to Program the Interfaces in June

Question 321

Multiple Choice

Mary is scheduled to program the interfaces in June. John will develop the training plan in July. Robert will test the system in July. Mark will be on sick leave during August and he has to write the documentation before he leaves. In order to make sure that the staff needed is available during these time periods, what process should be utilized?


A) systems analysis
B) implementation
C) resource allocation
D) Gantt chart