The production scheduler for a bottleneck resource should:
A) schedule additional preventive maintenance for the resource.
B) ensure a constant queue of work waiting to be processed.
C) increase production lot sizes to increase utilization of resources.
D) implement pull signals for production of the bottleneck resource.