Solved

Customer Demand Is 120 Units Per Week

Question 45

Multiple Choice

Customer demand is 120 units per week. The company works on a 9-hour shift per day, 5-day per week basis. Each shift has a ½-hour lunch break and two 15-minute coffee breaks. The cycle time is 12 minutes. To meet demand, production must occur at the rate of one unit every:


A) 12 minutes.
B) 20 minutes.
C) 22.5 minutes.
D) 28 minutes.

Correct Answer: