Multiple Choice
AB Developers signs a contract with CL Corp., agreeing to build a $20 million office for the corporation. The construction contract was substantially performed. There were, however, a few minor breaches of the contract by AB Developers that made CL Corp. incur damages worth $10,000. Which of the following is most likely to be true in this scenario?
A) Since there was a breach of contract, CL Corp. may not pay any compensation to AB Developers.
B) CL Corp. needs to pay the full price under the contract since the work was substantially performed.
C) CL Corp. needs to pay the full price under the contract less the damages suffered by it.
D) AB Developers needs to pay nominal damages to CL Corp. for breach of contract.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Punitive damages are damages paid to the
Q2: What constitutes satisfactory performance in a contract?
Q4: If a debtor tells a creditor "I
Q5: An offer to pay money in satisfaction
Q6: A debt that has been prohibited from
Q7: A f orce majeure clause in
Q8: If performance in a contract becomes extremely
Q9: Which of the following statements best describes
Q10: Which of the following statements is true
Q11: If an act is legal at the