​Estimating the Effort Required and Identifying Task Dependencies Is Usually

Question 21

Multiple Choice

​Estimating the effort required and identifying task dependencies is usually part of the work to create what?


A) The project iteration schedule
B) ​The detailed work schedule
C) The project time estimate
D) ​The critical path