A risk mitigation strategy should produce an action plan that identifies that includes all of the following except:


A) Roles and responsibilities for developing the strategy
B) Resources required to carry out the planned actions
C) Conditions present in order for risk level to be acceptable
D) A way to get rid of the risk completely