Eva, the Owner of Eva's Second Time Around Wedding Dresses

Question 5

Multiple Choice

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:
Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:   If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in her shop today? A) 2 jobs B) 2.33 jobs C) 2.4 jobs D) 2.67 jobs E) 3 jobs
If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in her shop today?


A) 2 jobs
B) 2.33 jobs
C) 2.4 jobs
D) 2.67 jobs
E) 3 jobs