A Production Line Is to Be Designed for a Job

Question 44

Multiple Choice

A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4 minutes, and 0.7 minutes. For a single production line with no parallel activities, the minimum cycle time in minutes is


A) 0.3.
B) 0.7.
C) 1.4.
D) 2.4.
E) 0.8.