Multiple Choice
What is the primary purpose of creating a work breakdown structure?
A) to draw the project plan as a chart or tree
B) to make sure important tasks are identified
C) so that all team members can see what others are working on
D) to assign budget numbers to tasks
E) to make sure team members can communicate effectively
Correct Answer:

Verified
Correct Answer:
Verified