Multiple Choice
A list of potential projects, several criteria, weights for those criteria, and criteria scores for those projects are all typically included on a(n) ___________ matrix.
A) Multiple criteria
B) Project screening
C) Project selection
D) Project elimination
E) Project assessment
Correct Answer: