Multiple Choice
A project professional has just been assigned manager of a project to develop a new advertising campaign for an established product. What is the second step the project manager should do?
A) Establish project priorities.
B) Define the project scope.
C) Verify the budget available.
D) Assign team members to work on the project.
E) Determine the required completion date.
Correct Answer: