Question 47

Question 47

Multiple Choice

What is the risk value of a risk whose impact score is 5, whose probability score is 5 and whose detection score is 1?


A) 5
B) 25
C) 125
D) 11
E) 10

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q42: The cost impact of a risk event

Q43: Choosing to move a concert indoors to

Q44: One common mistake made early in the

Q45: Risk events that occur in the early

Q46: Identify and briefly describe the four steps

Q48: Flooding would be devastating to the project;

Q49: Contingency reserves are set up to cover

Q50: The likelihood of a risk occurring _

Q51: Having an environment where identified risks are

Q52: The risk assessment form contains all of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines