A Project Scheduler Is Working on a Project That Technically

Question 46

Multiple Choice

A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?


A) Technical
B) People
C) Equipment
D) Physical
E) Materials

Correct Answer: