Multiple Choice
A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?
A) Technical
B) People
C) Equipment
D) Physical
E) Materials
Correct Answer:

Verified
Correct Answer:
Verified
Q41: A special truck that is needed on
Q42: All of the following are types of
Q43: A project manager has two engineers assigned
Q44: When the work in an activity is
Q45: The shortage of memory chips to produce
Q47: If resources are not adequate to meet
Q48: Identify and give an example of the
Q49: Identify and briefly describe two ways to
Q50: A(n) _ constraint addresses the sequence in
Q51: If it becomes necessary to delay one