In Reviewing the Status of a Project with Top Management

Question 7

Multiple Choice

In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as __________ constrained.


A) time
B) quality
C) cost
D) performance
E) resource

Correct Answer: