Multiple Choice
Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, what would be the second activity you would crash and how many days can you crash it?
A) A for 2 days
B) B for 2 days
C) C for 1 day
D) B for 1 day
E) A for 1 day