Analysis of data for an autoregressive forecasting model produced the following tables:
The actual values of this time series, y, were 228, 54, and 191 for May, June, and July, respectively.The predicted (forecast) value for August is ___.
A) 174.41
B) 83.67
C) 218.71
D) 36.91
E) 191