Multiple Choice
In setting up a kanban control system you need to determine the number of kanban card sets needed. If the expected demand during lead time is 25 per hour, the safety stock is 20 percent of the demand during lead time, the container size is 5, and the lead time to replenish an order is 5 hours, what the number of kanban card sets is needed?
A) 5
B) 20
C) 27
D) 30
E) 34
Correct Answer:

Verified
Correct Answer:
Verified