For a Particular Assertion, Control Risk Is the Risk That

Question 9

Multiple Choice

For a particular assertion, control risk is the risk that:


A) a material misstatement will occur in the accounting process.
B) controls will not detect a material misstatement that occurs.
C) audit procedures will fail to detect a weak control system.
D) the prescribed control procedures will not be applied uniformly.
E) an immaterial misstatement will occur in the accounting process.

Correct Answer: