Multiple Choice
Exhibit 17-2
In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:
-Refer to Exhibit 17-2. Assuming the performance obligation is satisfied over time, what would be the balance in Construction in Progress at the end of 2017?
A) $557,600
B) $659,600
C) $680,000
D) $782,000