A Flexible Budget Graph for the Assembly Department Shows the Following

Question 73

Essay

A flexible budget graph for the Assembly Department shows the following:
1. At zero direct labor hours, the total budgeted cost line intersects the vertical axis at $60,000.
2. At normal capacity of 50,000 direct labor hours, the line drawn from the total budgeted cost line intersects the vertical axis at $180,000.
Instructions
Develop the budgeted cost formula for the Assembly Department and identify the fixed and variable costs.

Correct Answer: