The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows:
​​
Use this information to answer the questions that follow. ​ The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: ​​    -The total factory overhead cost variance is A)  $2,000 favorable B)  $5,000 unfavorable C)  $2,500 unfavorable D)  $5,000 favorable
-The total factory overhead cost variance is


A) $2,000 favorable
B) $5,000 unfavorable
C) $2,500 unfavorable
D) $5,000 favorable