Robin Construction Company began a long-term contract in 2019.The contract price was $800,000.The estimated cost of the contract at the time it was begun was $500,000.The actual cost incurred in 2019 was $350,000.The contract was completed in 2020 and the cost incurred that year was $125,000.Under the percentage of completion method:


A) Robin should report $300,000 of income in 2019.
B) Robin should report $90,000 of income in 2020.
C) Robin will receive interest (under the look-back method) on the underpayment of taxes in 2019.
D) Robin should report $325,000 of income in 2019.