If the standard quantity (SQ) , actual quantity (AQ) , standard price (SP) , and actual price (AP) are 350 units, 400 units, $12, and $13 respectively, then the total budget variance is _____.
A) $1,000 favorable
B) $250 favorable
C) $250 unfavorable
D) $1,000 unfavorable
Correct Answer:

Verified
Correct Answer: