Multiple Choice
Green Company planned to produce 12,000 units.Processing required 16,000 machine hours at a cost of $15,000 + $10.50 per machine hour.Actual sales were 14,000 units requiring 20,000 machine hours.Actual processing cost was $222,000._____ is the static-budget variance for processing.
A) $39,000 favorable
B) $39,000 unfavorable
C) $42,000 favorable
D) $42,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified