A Cost That Should Be Ignored When Evaluating a Project

Question 15

Multiple Choice

A cost that should be ignored when evaluating a project because that cost has already been incurred and cannot be recouped is referred to as a(n) :


A) fixed cost.
B) forgotten cost.
C) variable cost.
D) opportunity cost.
E) sunk cost.

Correct Answer: