Bachmann Products, Inc., has found that new products follow a learning curve. The first two units have been completed with the following results:
-
How much time will be needed to complete the 8th unit?
A) 74.00 hours.
B) 57.80 hours.
C) 56.00 hours.
D) 49.13 hours.