Reyes Corporation applies overhead using an actual costing approach. Budgeted factory overhead was $266,400, budgeted machine-hours were 18,500. Actual factory overhead was $287,920, actual machine-hours were 19,050.
- How much overhead would be applied to production?
A) $266,400.
B) $274,320.
C) $279,607.
D) $287,920.